The essential reasoning of the design of a truss bridge with a Knex kit is
to allow a hands on experience with a realistic approach for a creative
design to be physically tested. Consequently, the pieces of Knex are being used. The design in Figure 1 and Figure 2 show the elevation and plan view of a specific designed truss bridge. The reasoning of this particular creation came about because the most cost effective and stable bridge created must be built for a competition. A limited amount of members and gussets were used because an excess amount of material will increase the cost dramatically; as a result, there were not a great number of Knex pieces used. In addition, the use of the triangular pattern and shape allows for maximum load bearing capacity compared to squares and circles.
A design of a bridge shown below is an example of a CAD drawing version of Knex of the elevation view.
The plan view of the design is shown below.
As the spread sheet shows, the cost of the bridge design should total to be approximately $189000. Only three main pieces were used. 46 3.375" long chords, 12 5.0" long chords, and 48 180 degree grooved gusset plates that were later connected were used to create the Knex bridge.
The original design of the bridge was hand drawn and needed to be completely redesign due to the limited amount of member sizes. In addition, the intended design began with more triangles intersecting the middle to reduce the amount of deformation of the squares because the geometry of squares will force the squares to become trapezoids under compression and tension. The amount of triangles was reduced because the cost of the bridge project was too extravagant. Consequently, the design seen in Figure 1 and Figure 2 were drawn up.
Throughout the process of designing this bridge, a number of things were taught. For example, the pieces are similar to real life were some pieces are readily available and made in industrial plants, while the customization of new pieces would have an extravagant cost. This showed that not every piece of member will be constantly available for the erection of a bridge. In addition, the planning and drawing of the bridge on a computer is a similar process to professional because real engineers and construction managers must have a clear understanding of other trades to complete a bridge. If a designer or any member of the project is unorganized or unable to communicate effectively, then misinterpretations will occur and the project will be prolonged; consequently, the cost of the project will increase while the productivity decreases.