In the previous week, the group
worked on extending the bridge from a twenty four inch span to a thirty six
inch span. This task turned out to be much harder than it was anticipated. The
team initially decided to keep the original design of the twenty four inch span
and to expand the bridge using the same pattern. After testing this idea, there
was little success. The team then added and took away many different aspects of
the design only to lead to failure. Each trial resulted in the bridge only
being able to hold approximately twenty to twenty five pounds.
After
much review and consideration, it was determined that the bridge needed to be
completely redesigned. Although the design for the twenty four inch span worked
very well, modifying it to reach thirty six inches would not work properly. The
new design is quite different but has many of the same elements. The bridge is
a lot taller than the first design was and included many different types of structure
beams on the inside of the bridge. However, some elements that remained the
same were the thickness of the bridge, the use of triangles, the technique to
allow bending and beams used on the sides of the bridge to minimize contortion.
This design for the bridge costs about $373,500 and can hold potentially thirty five
pounds.